Urban Development
ministry reviewed the 6 Metro rail projects going on across the country,
construction work in respect of Ahmedabad Metro Rail Project has begun within
three months of the project being sanctioned by the central government with the
Special Purpose Vehicle for execution of the project, MEGA (Metro –Link Express
for Gandhinagar and Ahmedabad) Company Limited commencing work for construction
of 6 km. Viaduct between Vastaral Gaam and Apparel Park. The Rs. 10,773 cr
project envisages 37.66 km of Metro Rail with and elevated portion of 31.43 km
and underground portion of 6.33 km.
Ahmedabad Metro
Project will have an East-West corridor of 20.53 km between Thatlej Gaam and
Vastrapur Gaam including the underground portion and fully elevated North-South
corridor of 17.23 km between APMC and Motera stadium. There will be a total of
32 stations.
Shri Madhusudhan
Prasad, Secretary (UD) during the review on Friday last has asked the six
Metros being implemented on 50:50 basis to ensure that there are no time and
cost overruns. He said that infrastructure projects are top priority for the
government and they are being monitored by the Prime Minister’s Office.
Kochi Metro
informed that 51% of work has been completed on Reach I from Aluva to Maharajas
and 17% of work on Reach II between Maharajas and Petta. 4883 of 5693 Piles,
731 of 1416 Piers and 862 of 2751 Girders have also been completed. Financial
progress has been reported to be 34%.
In respect of
Bengaluru Metro, physical and financial progress of about 92% has been
reported. The entire network of 42.30 kms., in Phase I will be complete in all
respects by December this year of which 38.30 km. would be operational for
public service and the balance 4 km would be ready for testing and
commissioning. This Metro has a North-South corridor of 24.20 km between Puttenahalli
and Nagasandra and East – West corridor of 18.10 km between Mysore Road and
Baiyyappanahalli. Three Reaches with a total length of 17 km with 16 stations
have so far been commissioned.
Regarding Chennai
Metro, Stage -1 comprising 7 stations and Viaduct of 10 km is set for revenue
operations soon. Commissioner of Metro Rail Safety has carried out Rolling
Stock inspection for this stage in the first week of this month. Out of the 42
train sets required, 9 from Brazil and 12 from Sri City, Chittor (AP) have been
received. Regarding other four Stages, works are in progress.
Nagpur Metro has
reported completion of demarcation of alignment on Airport –MIHAN , Automative
Square to Zero Mile and Prajapatinagar – Dosar Vaisya Chowk sections amounting
to 55% of total alignment. DMRC has been
assigned the Consultancy work of preparation of bid document for appointment of
General Consultant and preparation of Design Basis Report. RITES has been
tasked with preparation of bid document and bid process management for
appointment of execution agency for the priority section between Airport and
MIHAN and bid document for appointment of Detailed Design Consultant and for
construction of Viaduct between Airport and Sitaburdi.
DMRC reported 70%
progress in civil works and overall physical progress of 57% in respect of
Phase-III Project and financial progress of 40%. This Phase is scheduled for
completion between May, 2015 and December, 2016.